Lien notice · Florida

Florida Lien Notice to the Homeowner (2026): Goes in the Contract

What a contractor hired directly by a homeowner must give the owner in Florida to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: On a direct contract over $2,500 for a one to four unit dwelling, print the statutory construction lien warning on the front page of the contract or on a separate page the owner signs and dates. On a $32,000 kitchen signed March 2 with work starting March 16: The warning had to be in the contract signed March 2; without it the lien is exposed if the owner was adversely affected.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Florida

Rule

Lien at stake

On a direct contract over $2,500 for a one to four unit dwelling, print the statutory construction lien warning on the front page of the contract or on a separate page the owner signs and dates.

Notice to the homeowner due

In the contract

In the written contract, front page or separate signed and dated page.

Source

Fla. Stat. 713.015

flsenate.gov (official), 2026 Florida Statutes; history ends at ch. 2007-221.

“against a person who has not been adversely affected”

A $32,000 kitchen in Florida

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

Yes

The warning had to be in the contract signed March 2; without it the lien is exposed if the owner was adversely affected.

The details

Deadline

At signing (the notice must be in the contract document; for an oral or implied contract, in a document that references the contract).

Required form

Statutory text, at least 12-point, capitalized, boldfaced type.

If you miss it

Missing notice does not bar the lien against a person who has not been adversely affected (713.015(2)); against an owner who was adversely affected, the lien can be barred.

Subs and suppliers

Lienors not in privity with the owner serve their own notice to owner under 713.06 (not read in this pass).

Florida lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Florida?

On a direct contract over $2,500 for a one to four unit dwelling, print the statutory construction lien warning on the front page of the contract or on a separate page the owner signs and dates.

What happens if a contractor misses the notice in Florida?

Missing notice does not bar the lien against a person who has not been adversely affected (713.015(2)); against an owner who was adversely affected, the lien can be barred.

Do subs and suppliers have to give notice in Florida?

Lienors not in privity with the owner serve their own notice to owner under 713.06 (not read in this pass).

Compare other states

More Florida rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.