Lien notice · California

California Lien Notice to the Homeowner (2026): Goes in the Contract, Lien Kept if Missed

What a contractor hired directly by a homeowner must give the owner in California to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: Put the statutory Mechanics Lien Warning in the home improvement contract (jobs over $500). A direct contractor owes a preliminary notice only to a construction lender, if there is one. On a $32,000 kitchen signed March 2 with work starting March 16: With no construction lender, nothing was needed by March 16 to keep the lien; the warning belonged in the March 2 contract as a licensing duty.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in California

Rule

Disclosure

Put the statutory Mechanics Lien Warning in the home improvement contract (jobs over $500). A direct contractor owes a preliminary notice only to a construction lender, if there is one.

Notice to the homeowner due

In the contract

Part of the written home improvement contract.

Source

Cal. Civ. Code 8200; Bus. & Prof. Code 7159(e)(4)

public.law mirror of leginfo, verified November 16, 2026 (leginfo.legislature.ca.gov could not be fetched). B&P 7159 read on the same mirror, shown as updated January 1, 2026.

“is required to give preliminary notice only to the construction lender”

A $32,000 kitchen in California

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

With no construction lender, nothing was needed by March 16 to keep the lien; the warning belonged in the March 2 contract as a licensing duty.

The details

Deadline

At signing, as part of the contract form. Lender preliminary notice, when there is a construction lender, is a separate step under Civil Code 8200 to 8204.

Required form

Heading 'Mechanics Lien Warning' with the statutory text; printed text at least 10-point, headings at least 10-point boldface (B&P 7159(c), (e)(4)).

If you miss it

Omitting the warning is cause for license discipline (B&P 7159(a)(5)); the section read does not take away the lien. Where there is a construction lender, preliminary notice to the lender is a necessary prerequisite to a valid lien claim (Civ. Code 8200(c), (e)(2)).

Subs and suppliers

Subs and suppliers must give preliminary notice to the owner, the direct contractor and any construction lender (Civ. Code 8200(a)); laborers are exempt.

California lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in California?

Put the statutory Mechanics Lien Warning in the home improvement contract (jobs over $500). A direct contractor owes a preliminary notice only to a construction lender, if there is one.

What happens if a contractor misses the notice in California?

Omitting the warning is cause for license discipline (B&P 7159(a)(5)); the section read does not take away the lien. Where there is a construction lender, preliminary notice to the lender is a necessary prerequisite to a valid lien claim (Civ. Code 8200(c), (e)(2)).

Do subs and suppliers have to give notice in California?

Subs and suppliers must give preliminary notice to the owner, the direct contractor and any construction lender (Civ. Code 8200(a)); laborers are exempt.

Compare other states

More California rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.