Lien notice · Arizona

Arizona Lien Notice to the Homeowner (2026): Due Within 20 Days of Starting

What a contractor hired directly by a homeowner must give the owner in Arizona to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: Serve the Arizona preliminary twenty day notice on the owner (and any construction lender) within 20 days after first furnishing labor or materials. On an owner-occupied dwelling, only someone with a written contract signed directly with the owner-occupant can lien at all. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing beyond the written contract was due by March 16; the 20-day notice had to be mailed by April 5.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Arizona

Rule

Lien at stake

Serve the Arizona preliminary twenty day notice on the owner (and any construction lender) within 20 days after first furnishing labor or materials. On an owner-occupied dwelling, only someone with a written contract signed directly with the owner-occupant can lien at all.

Notice to the homeowner due

Within 20 days of starting

First class mail with a certificate of mailing, or registered or certified mail, postage prepaid; service is complete on mailing.

Source

A.R.S. 33-992.01, 33-1002

azleg.gov (official), current online A.R.S.; 33-992.01 and 33-1002 both read.

“not later than twenty days after the claimant has first furnished labor”

A $32,000 kitchen in Arizona

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing beyond the written contract was due by March 16; the 20-day notice had to be mailed by April 5.

The details

Deadline

Not later than 20 days after first furnishing labor, services or materials to the jobsite.

Required form

Statutory form in 33-992.01 (bold owner warning). A notice that is otherwise compliant is not defective for missing bold type or type size.

If you miss it

The notice is 'a necessary prerequisite to the validity of any claim of lien' (33-992.01(B)). A late notice saves only work furnished within 20 days before service and after (33-992.01(E)). No written contract with the owner-occupant, no lien (33-1002(B)).

Subs and suppliers

Subs and suppliers have no lien on an owner-occupied dwelling because they have no written contract with the owner-occupant (33-1002(B)).

Arizona lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Arizona?

Serve the Arizona preliminary twenty day notice on the owner (and any construction lender) within 20 days after first furnishing labor or materials. On an owner-occupied dwelling, only someone with a written contract signed directly with the owner-occupant can lien at all.

What happens if a contractor misses the notice in Arizona?

The notice is 'a necessary prerequisite to the validity of any claim of lien' (33-992.01(B)). A late notice saves only work furnished within 20 days before service and after (33-992.01(E)). No written contract with the owner-occupant, no lien (33-1002(B)).

Do subs and suppliers have to give notice in Arizona?

Subs and suppliers have no lien on an owner-occupied dwelling because they have no written contract with the owner-occupant (33-1002(B)).

Compare other states

More Arizona rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.